AS ON 01.05.2025

    TOWER-1
  • 2nd floor slab casting done
  • Landscape area RCC wall working progress and ground floor brick, plaster work in progress.
    TOWER-2
  • Part ground floor slab completed.
  • Part 1st floor slab casting done.
  • Balance part ground floor slab casting completed & 1st floor level slab reinforcement binding work in progress.
  • Ground floor anchor-2 RCC wall & inside brick work completed.
    TOWER-3
  • Roof slab casting done.
  • Above roof work in progress.
  • Finishing work in progress.
  • Model flat completed.
    TOWER-4
  • Roof slab casting work completed.
  • Above roof parapet reinforcement & shuttering work progress.
  • Internal plumbingwork in progress.
    TOWER-5
  • Roof slab casting done.
  • Above roof parapet reinforcement & shuttering work progress.
  • 10th floor brick work done.
  • 1st to 9th floor plaster completed 
  • 11th floor brick working progress.
    TOWER-6
  • 7th floor slab casting done.
  • 8th floor level slab reinforcement & mivan shuttering work in progress.
  • 3rd floor brick work and plaster completed.
    TOWER-7
  • Roof slab completed.
  • Above roof work in progrss
  • Internal plumbing work in progrss.
  • Water proofing work in progress.
  • Flooring work in progress.
    ROAD
  • T-7 ,T-6 BACK SIDE & T-1, T-2 FONT SIDE INFRA & ROAD WORKING PROGRESS.