AS ON 01.05.2025
TOWER-1
2nd floor slab casting done
Landscape area RCC wall working progress and ground floor brick, plaster work in progress.
TOWER-2
Part ground floor slab completed.
Part 1st floor slab casting done.
Balance part ground floor slab casting completed & 1st floor level slab reinforcement binding work in progress.
Ground floor anchor-2 RCC wall & inside brick work completed.
TOWER-3
Roof slab casting done.
Above roof work in progress.
Finishing work in progress.
Model flat completed.
TOWER-4
Roof slab casting work completed.
Above roof parapet reinforcement & shuttering work progress.
Internal plumbingwork in progress.
TOWER-5
Roof slab casting done.
Above roof parapet reinforcement & shuttering work progress.
10th floor brick work done.
1st to 9th floor plaster completed
11th floor brick working progress.
TOWER-6
7th floor slab casting done.
8th floor level slab reinforcement & mivan shuttering work in progress.
3rd floor brick work and plaster completed.
TOWER-7
Roof slab completed.
Above roof work in progrss
Internal plumbing work in progrss.
Water proofing work in progress.
Flooring work in progress.
ROAD
T-7 ,T-6 BACK SIDE & T-1, T-2 FONT SIDE INFRA & ROAD WORKING PROGRESS.